The First Avenue Grade Separation Project, which has been broken into five phases, is currently in phase three. Crews are working on bridge abutments, driving pile and setting forms. A mild winter is helping get work back on schedule after some delays. Watch the video to find out more. For more information on the First Avenue Grade Separation Project, visit www.icgov.org/firstavenueproject

Date of publication

Tuesday, March 01, 2016