Description: 

Construction of Glendale Park Improvements shall include, but not limited to, removal and installation of sidewalk, ADA curb ramps and reconstruction of the entrance to the parking lot of Wetherby Park.

Project Schedule Information: 

Specified Start Date: June 6, 2022
Substantial Completion: September 16, 2022
Final Completion: September 30, 2022
Liquidated Damages: $250 per day

Date plans available: 
Wednesday, April 20, 2022
Obtain from: 

Technigraphics, a division of Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City. Iowa 52240
Phone: (319) 354-5950
Toll-Free: (800) 779-0093
https://rapidsrepro.com/iowa-city/

Cost: 

None

Pre-bid Conference: 

Date:  April 28, 2022
Time:  10:00 a.m.
Location:  Engineering Conference Room, City Hall, 410 E Washington Street, Iowa City, Iowa

Project Status

Awarded

Awardee

Bockenstedt Excavating

Engineer's Estimate

$93,000

Bid Deadline

Tuesday, May 10, 2022 - 3:00pm

Council Award Date

Tuesday, May 17, 2022