Construction of Wetherby Park CDBG Trail Improvements including demolition of existing gravel, a new PCC trail, finish grading, seeding, and associated work as shown on the plans.

Project Schedule Information: 

Specified Start Date:  September 21, 2020
Substantial Completion Date:  November 15, 2020
Final Completion Date:  May 1, 2021
Liquidated Damages: $500 per day

Date plans available: 
Wednesday, August 19, 2020
Obtain from: 

Rapid Reproductions / Technigraphics
415 Highland Avenue, Suite 100
Iowa City, IA   52240
319-356-5950

Cost: 

$50 per plan set.  Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.

Pre-bid Conference: 

None

Project Status

Awarded

Awardee

McComas-Lacina Construction

Engineer's Estimate

$222,000

Bid Deadline

Tuesday, September 8, 2020 - 2:00pm

Council Award Date

Tuesday, September 15, 2020