Description:
Construction of Wetherby Park CDBG Trail Improvements including demolition of existing gravel, a new PCC trail, finish grading, seeding, and associated work as shown on the plans.
Project Schedule Information:
Specified Start Date: September 21, 2020
Substantial Completion Date: November 15, 2020
Final Completion Date: May 1, 2021
Liquidated Damages: $500 per day
Date plans available:
Wednesday, August 19, 2020
Obtain from:
Rapid Reproductions / Technigraphics
415 Highland Avenue, Suite 100
Iowa City, IA 52240
319-356-5950
Cost:
$50 per plan set. Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.
Pre-bid Conference:
None