Description: 

Demolition of existing ammonia feed equipment and upgrading the existing chlorine gas feed equipment and eye washes.

Project Schedule Information: 

Specified Start Date:  January 3, 2023
Substantial Completion Date:  May 15, 2023
Final Completion Date:  June 12, 2023
Liquidated Damages:  $100.00 per day

Date plans available: 
Wednesday, November 2, 2022
Obtain from: 

Rapids Reproductions, Inc./Technigraphics
415 Highland Avenue, Suite 100
Iowa City, IA  52240

319-354-5950

Cost: 

None

Pre-bid Conference: 

Date:  November 22, 2022
Time:  10:00 a.m.
Location:  Water Treatment Plant, 80 Stephen Atkins Dr, Iowa City, Iowa

Project Status

Awarded

Engineer's Estimate

$192,000

Bid Deadline

Tuesday, November 29, 2022 - 3:00pm

Council Award Date

Tuesday, December 6, 2022

Contact