This project involves water main system improvements to create an east pressure zone within the existing Iowa City water distribution. Construction will generally include trenchless installation of approximately 300 feet of new water main, hydrants, and values, concrete roadway and sidewalk patching and reconstruction of pedestrian curb ramps at various sites within the City.
Overall
Specified Start Date: April 20, 2020
Substantial Completion Date: August 28, 2020
Liquidated Damages: $500 per day
Milestones
North Dodge Street Site
10 Calendar Days
Incentive/Disincentive: $1,000 per day
Maximum Incentive: $5,000
Kimball Road Site
15 Calendar Days
Incentive/Disincentive: $500 per day
Maximum Incentive: $5,000
Muscatine Avenue Site
All work at the intersections of Muscatine Avenue and Dover Street and Muscatine Avenue and Southlawn Drive shall be completed between June 15th and July 31st.
Technigraphics / Rapids Reproductions
415 Highland Avenue Suite 100
Iowa City, IA 52240
319-354-5950
$30 per plan set. Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.
None