Description: 

This project involves the removal, repair and/or replacement of existing primary and secondary clarifier equipment at the Iowa City Wastewater Treatment Facility. The four original clarifiers that were constructed circa 1989 still have their original carbon steel mechanisms that are severely corroded and are nearing the end of their useful life.  All new and repaired equipment will have new protective coatings applied.

Project Schedule Information: 

Specified Start Date:  April 4, 2017
Final Completion Date:  December 1, 2017
Liquidated Damages:  $250 per day

Date plans available: 
Thursday, February 9, 2017
Obtain from: 

Rapids Reproductions / Technigraphics
415 Highland Avenue, Suite 100
Iowa City, IA   52240
319-354-5950

Cost: 

$25 per plan set.  Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.

Pre-bid Conference: 

Date:  February 28, 2017
Time:  1:30 p.m.
Location:  Wastewater Treatment Facility
                4366 Napoleon Street
                Iowa City, IA  

Project Status

Awarded

Awardee

Fab Tech Wastewater Solutions

Engineer's Estimate

$281,750

Bid Deadline

Wednesday, March 8, 2017 - 2:30pm

Council Award Date

Tuesday, March 21, 2017

Contact