Description: 

The project involves installation of landscape improvements along two roadway corridors in Iowa City.  The project includes all materials, labor and equipment necessary for construction of project improvements.  Approximate quantities include: 164 shade trees, 118 ornamental trees, 171 shrubs, 8,193 perennials/bulbs, 628 square feet of face segmental retaining wall, mulch, traffic control and miscellaneous related work.

 

 

Project Schedule Information: 

Project Completion Date:  December 31, 2016
Early Start Date:  August 15, 2016
Late Start Date:  September 15, 2016
Liquidated Damages:  $200 per day
Calendar Day Completion Deadline:  45 working days

Date plans available: 
Wednesday, June 22, 2016
Obtain from: 

Rapids Reproductions / Technigraphics
415 Highland Ave., Suite 100
Iowa City, IA   52240
319-354-5950

Cost: 

$25 deposit per plan set, and a separate non-refundable $10 shipping and handling fees for plans that are sent through postal mail.

Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.

Pre-bid Conference: 

None

Project Status

Rejected

Engineer's Estimate

$261,370

Bid Deadline

Wednesday, July 13, 2016 - 2:30pm