Approximately 900 feet of 8” PVC water main installed by directional drill method on the west side of Spruce Street between Deforest Avenue and Friendly Avenue/Lower Muscatine Road. In addition, the construction activities will include the associated copper water services, traffic control, and sidewalk and pavement removal and restoration.
Specified Start Date: March 2, 2020
Substantial Completion Date: April 30, 2020
Final Completion Date: May 30, 2020
Liquidated Damages: $500 per day