Description:
The Project will involve the installation of approximately 1400 linear feet of sidewalk, 905 linear feet of storm sewer pipe and associated structures, and 1082 square yards of new HMA surface for the shoulder along Scott Blvd and the parking lot at Rita’s Ranch Dog Park, and associated landscape restoration and is located along Scott Boulevard, between Silver Lane and Court Hill Trail in Iowa City, Iowa
Project Schedule Information:
Specified Early Start Date: September 20, 2022
Specified Late Start Date: April 3, 2023
Substantial Completion Date: June 16, 2023
Final Completion Date: June 30, 2023
Liquidated damages: $250 per day