Description: 

The Project will involve the following: site work and installation of Kenneth Snelson sculpture “Four Modular Piece” at Riverfront Crossings Park, 1001 South Clinton Street, Iowa City, Iowa 52240.  Work includes installing new concrete pavement, subbase and draintile; concrete sculpture columns, exterior sculpture lighting; and landscaping.

Project Schedule Information: 

Specified Start Date: July 22, 2019
Final Completion:  November 15, 2019
Liquidated Damages:  $250 per day

Date plans available: 
Wednesday, June 19, 2019
Obtain from: 

Rapids Reproductions
415 Highland Avenue, Suite100
Iowa City, IA   52240
319-354-5950

Cost: 

$50 per plan set.  Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.

Pre-bid Conference: 

Date:  June 27, 2019
Time:  1:30 p.m.
Location:  Helling Conference Room, City Hall, 410 E Washington Street, Iowa City, Iowa

Project Status

Awarded

Awardee

All American Concrete

Engineer's Estimate

$450,000

Bid Deadline

Tuesday, July 9, 2019 - 3:00pm

Council Award Date

Tuesday, July 16, 2019

Contact