Description: 

Furnish all labor, equipment and materials required for complete brick pavement replacement, utility upgrades (water main, irrigation, electrical, telecom, etc.), lighting, landscaping, site furnishings and installation of a permanent stage near the weather dance fountain.

Project Schedule Information: 

Phase 1A (Dubuque St. and College St. Intersection):
   Late Start Date: April 30, 2018
   Substantial Completion: July 31, 2018
   Incentive/Disincentive: $1,000 per day
   Maximum Incentive: $10,000
Phase 1 Alley Closure:
   14 Allowable Closure Days
   Incentive/Disincentive: $1,000 per day
   Maximum Incentive: $5,000 
Phase 1B (Dubuque Street):
   Late Start Date: April 30, 2018
   Substantial Completion: October 31, 2018 
   Incentive/Disincentive: $1,000 per day
   Maximum Incentive: $10,000  
Phase 2 (College Street):
   Early Start Date: May 13, 2019
   Substantial Completion: October 31, 2019
   Incentive/Disincentive: $1,000 per day
   Maximum Incentive: $10,000

Date plans available: 
Wednesday, February 21, 2018
Obtain from: 

Rapids Reproductions / Technigraphics
415 Highland Avenue, Suite 100
Iowa City, IA   52240
319-354-5950

Cost: 

$50 per plan set.  Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.

Pre-bid Conference: 

Date:  March 19, 2018
Time:  1:30 p.m.
Location:  Emma J Harvat Hall
                City Hall
                Iowa City, IA

Project Status

Awarded

Awardee

Portzen Construction

Engineer's Estimate

$6,800,000

Bid Deadline

Tuesday, March 27, 2018 - 3:00pm

Council Award Date

Monday, April 2, 2018

Contact

Document(s)