The 2015 project focuses on concrete floor repairs and membrane patching in the Dubuque Street Ramp. Additional efforts in this facility include repairs to deteriorated concrete beams, expansion joints, stair tower tread and risers and interior facade lintels, along with other isolated structural and waterproofing repairs throughout the garage. Also included are smaller repair projects within three additional ramps: Capitol Street Ramp, Chauncey Swan Ramp and Tower Place Parking Ramp.
Final completion date: October 2, 2015
Milestone dates as noted in bid documents.
Technigraphics/Rapid Reproductions
415 Highland Avenue, Suite 100
Iowa City, Iowa 52240
319-354-5950
800-779-0093
$65 per plan set. $50 refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.
Date: Thursday, May 14, 2015
Time: 10 a.m.
Location: Tower Place Parking Ramp
Conference Room
335 Iowa Avenue
Iowa City, Iowa