Pavement reconstruction between Benton Street and Hwy 1, sidewalk infill along the east side of Orchard Street, ADA compliant pedestrian curb ramps and pedestrian signal improvements, water main, storm sewer, and sanitary sewer improvements.
Late Start: September 6, 2021
Working Days: 120
Liquidated Damages: $500 per day
Technigraphics/Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City, IA 52240
319-354-5950
800-779-0093
None
None
Midwest Concrete