Description:
The Project will involve the installation of approximately 1,300 linear feet of storm sewer pipe and associated structures, approximately 4,200 square yards of concrete pavement replacement, approximately 1,500 square yards of sidewalk replacement and associated landscape restoration and is located at, and adjacent to, the intersection of E Washington Street and North Westminster Street in Iowa City, Iowa.
Project Schedule Information:
Specified Start Date: June 2, 2022
Final Completion Date: May 31, 2023
Liquidated Damages: $240 per day
Date plans available:
Wednesday, April 20, 2022
Obtain from:
Rapids Reproduction, Inc.
415 Highland Ave.
Iowa City, IA 52240
Phone: (319) 354-5950
iowacity@rapidsrepro.com
Cost:
None
Pre-bid Conference:
Date: May 2, 2022
Time: 2:00 p.m.
Location: City Hall, 410 E Washington Street, Iowa City, Iowa