Description: 

Provide all labor, equipment and materials for restriping the existing pavement to a 3-lane section with buffered bike lanes, traffic signal replacements at three intersections, the addition of a right turn lane at the Benton Street intersection and the replacement of existing roadway lighting (Melrose Avenue north to City Limits); including and all other miscellaneous associated work.

Project Schedule Information: 

Specified Completion Date:  May 31, 2019
Late Start Date:  July 23, 2019
Liquidated Damages:  $1,000 per day
*Please refer to plans and specifications for additional information relating to interim project milestones and associated liquidated damages.

Date plans available: 
Wednesday, May 30, 2018
Obtain from: 

Rapids Reproductions / Technigraphics
415 Highland Avenue, Suite 100
Iowa City, IA   52240
319-354-5950

Cost: 

$30 per plan set
Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.

Pre-bid Conference: 

None

Project Status

Awarded

Awardee

All American Concrete

Engineer's Estimate

$1,465,000

Bid Deadline

Tuesday, June 26, 2018 - 3:00pm

Council Award Date

Tuesday, July 3, 2018

Contact