Description:
The supply and installation of new playground equipment in replacement of the existing equipment located at Mercer Park.
Project Schedule Information:
Specified Start Date: November 23, 2015
Completion Date: May 13, 2016
Liquidated Damages: $100 per day
Date plans available:
Wednesday, October 21, 2015
Obtain from:
Engineering Division
City of Iowa City
410 E Washington Street
Iowa City, IA 52240
319-356-5140
Cost:
$50 Deposit - refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.
Pre-bid Conference:
None