The Project, located at the Mercer Park Aquatic Center and Scanlon Gym, 2701 Bradford Dr, Iowa City, IA 52240, will include demolition of existing air handling equipment, main ductwork, and other related components that serve the natatorium. New installation will include an owner provided and contractor installed dehumidification unit located on grade just to the west of the natatorium. Related components, including piping, ductwork, and electrical will be the responsibility of the successful bidder.
Specified Start Date Outside Work: July 19th, 2021
Specified Start Date Inside Work: August 16th, 2021
Substantial Completion: September 17th, 2021
Liquidated Damages: $240 per day
Rapids Reproduction, Inc.
415 Highland Ave.
Iowa City, IA 52240
Phone: (319) 354-5950
iowacity@rapidsrepro.com
$30 per plan set. Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.
Date: January 28, 2021
Time: 2:00 p.m.