Description: 

The project limits are from Brookland Park Drive to approximately 200 feet south of the Intersection of Melrose Court and Melrose Avenue.  Project generally includes: sanitary sewer pipes, sanitary sewer manholes, sanitary sewer service reconnection, sanitary sewer abandonment, storm sewer pipes, storm sewer intakes and manholes, storm sewer abandonment, street pavement, driveways, sidewalk, and seeding.

Project Schedule Information: 

Specified Start Date: May 3, 2021
Substantial Completion: August 25, 2021
Final Completion: September 24, 2021
Liquidated Damages: $750 per day

Date plans available: 
Wednesday, March 24, 2021
Obtain from: 

Technigraphics, a division of Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City, Iowa 52240
Phone:(319) 354-5950
Toll-Free:(800) 779-0093
https://rapidsrepro.com/iowa-city/</p>

Cost: 

$20.00 per set. Deposit refundable if plans/specifications are returned in reusable condition within 14 days of award of project.

Pre-bid Conference: 

Date:  Monday, April 5, 2021
Time:  2:00 p.m.
Location:  This will be a virtual meeting with invitations being sent to plan holders list maintained by Technigraphics

Project Status

Awarded

Awardee

Midwest Concrete

Engineer's Estimate

$525,000

Bid Deadline

Tuesday, April 13, 2021 - 3:00pm

Council Award Date

Tuesday, April 20, 2021

Contact