The McCollister Street Extension Project includes excavation, 17,500 YDS of PCC pavement, 8,300 YDS of sidewalk, storm sewer, sanitary sewer, 4,000 LF of water main and appurtenances, and other miscellaneous work. Located between Gilbert Street and Sycamore Street, just south of Langenberg Avenue.
Specified Start Date: April 13, 2020
Substantial Completion: October 30, 2020
Final Completion: November 20, 2020
Liquidated damages: $500.00 per day
Stage 2A work is considered critical to the City of Iowa City and shall be open to traffic before August 15, 2020, as shown on the plans:
Specified Start Date: June 15, 2020
Substantial Completion: August 7, 2020
Final Completion: August 15, 2020
Liquidated damages: $500.00 per day
Technigraphics/Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City, IA 52240
Telephone: 319-354-5950
Fax: 319-354-8973
Toll Free: 800-779-0093
$30 per plan set. Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.
Date: January 15, 2020
Time: 10:30 a.m.
Location: Helling Conference Room, City Hall, 410 E Washington Street, Iowa City, Iowa