Description:
Approximately 290 LF of 8” sanitary sewer replacement, sewer lateral replacement, 1,400 SY of street pavement removal and replacement, 490 SY of sidewalk, 230 SY of driveway, ADA ramps, water main modifications, and other related work.
Project Schedule Information:
Specified Start Date: June 5, 2023
Substantial Completion Date: August 21, 2023
Final Completion: September 20, 2023
Liquidated Damages: $500 per day
Date plans available:
Wednesday, February 8, 2023
Obtain from:
Rapids Reproductions
415 Highland Ave, Suite 100
Iowa City, Iowa 52240
Phone: (319) 354-5950
Pre-bid Conference:
Date: Feburary 21, 2023
Time: 2:00 p.m.
Location: 410 E Washington Street, Iowa City, Iowa, City Hall, Engineering Conference Room, 3rd Floor