Description: 

The Project will involve the following: for the West Iowa Avenue Bridge, removal and replacement of four (4) separate expansion joints with new compressible expansion joint seals, associated concrete floor and edge repairs adjacent to the expansion joints, and repair of deteriorated concrete on the north and south sidewalks and curbs.

Project Schedule Information: 

Specified Start Date:  June 15, 2020
Substantial Completion Date:  July 24, 2020
Final Completion Date:  August 14, 2020
Liquidated Damages:   $500 per day

Date plans available: 
Wednesday, April 8, 2020
Obtain from: 

Technigraphics
415 Highland Ave, Suite 100
Iowa City, Iowa 52240
Phone (319) 354-5950, Fax (319) 354-8973, Toll Free: (800) 779-0093

Cost: 

$20 per plan set.  Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.

Pre-bid Conference: 

None

Project Status

Awarded

Awardee

Minturn, Inc.

Engineer's Estimate

$100,000

Bid Deadline

Wednesday, April 29, 2020 - 2:30pm

Council Award Date

Tuesday, May 5, 2020