The Project will involve the following: replacing two aging mechanically cleaned bar screens and associated electrical and controls equipment; adding washing presses and a conveyance system to a new screenings storage building addition; replacing the upstream influent channel slide plates with slide gates; adding a new dewatering station for septic haulers that transport high grit (car wash) loads; utility relocations; and new pavement. The project is located at the Wastewater Treatment Facility, 4366 Napoleon Street Southeast, Iowa City, Iowa 52240
Start Date: January 3, 2022
Substantial Completion: September 30, 2022
Final Completion: October 31, 2022
Liquidated Damages: $240 per day
Rapids Reproduction, Inc.
415 Highland Ave.
Iowa City, IA 52240
Phone: (319) 354-5950
iowacity@rapidsrepro.com
None
Date: November 30, 2021
Time: 10:30am
Location: Iowa City Wastewater Treatment Facility, 4366 Napoleon Street SE, Iowa City, Iowa