Description: 

The project will involve the following: approximately 1,600 feet of 12” PVC water main installed by directional drill method on the north side of Highway 1 between Westport Plaza (Walmart Entrance) and Hawk Ridge Drive.  In addition, the construction activities will include the associated fittings, valves, hydrants, traffic control, shared use path removal and restoration, and seeding.

Project Schedule Information: 

Specified Start Date: March 1, 2022
Substantial Completion: May 31, 2022
Final Completion: June 30, 2022
Liquidated Damages: $500 per day

Date plans available: 
Wednesday, December 1, 2021
Obtain from: 

Technigraphics, a division of Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City, Iowa 52240

Phone: (319) 354-5950
Toll-Free: (800) 779-0093
https://rapidsrepro.com/iowa-city/

Cost: 

None

Pre-bid Conference: 

Date: Tuesday, December 14, 2021
Time: 2:00 P.M.
Location: If the meeting is not conducted in person due to the health and safety concerns from COVID-19, this meeting will be an electronic meeting using the Zoom Meetings.  Information for this meeting will be distributed by the City Engineering Division to prospective bidders on the Project Plan Holders List.  For information on how to participate in the electronic meeting, please contact the City Engineering Division at (319) 356-5144.

Project Status

Awarded

Awardee

Maxwell Construction

Engineer's Estimate

$460,000

Bid Deadline

Tuesday, December 21, 2021 - 3:00pm

Council Award Date

Tuesday, January 4, 2022

Contact