Removal of existing wooden pedestrian bridge and construction of a new pre-engineered steel bridge and concrete abutments over North Branch of Ralston Creek in Hickory Hill Park near First Avenue in Iowa City. The project will also include clearing and grubbing, minor streambank stabilization and granular trail repairs.
Specified Start Date: February 27, 2017
Specified Completion Date: May 15, 2017
Liquidated Damages: $250 per day
Engineering Division
City of Iowa City
410 E Washington Street
Iowa City, IA 52240
319-356-5140
$15 deposit per plan set. Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.
Date: Wednesday, February 1, 2017
Time: 10:00 a.m.
Location: Engineering Conference Room, 3rd Floor, City Hall, 410 E Washington Street, Iowa City, Iowa