Description: 

This project includes removal and replacement of aggregate trail, installation of water bars to improve site drainage, installation of drain tile and subdrains, construction of (1) new pedestrian bridge (steel) and associated abutments/revetment, fabrication and installation of park trail and interpretive signs and associated restoration.

Project Schedule Information: 

Specified Start Date:  January 2, 2019
Substantial Completion:  June 1, 2019
Final Completion:  June 15, 2019
Liquidated Damages:  $500 per day

Date plans available: 
Wednesday, November 21, 2018
Obtain from: 

Technigraphics / Rapid Reproductions
415 Highland Avenue, Suite 100
Iowa City, IA   52240
319-354-5950

Cost: 

$40 per plan set.  Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.

Pre-bid Conference: 

None

Project Status

Awarded

Awardee

Calacci Construction

Engineer's Estimate

$306,000

Bid Deadline

Monday, December 10, 2018 - 3:00pm

Council Award Date

Tuesday, December 18, 2018