The Hickory Hill Park Improvements Project includes clearing and grubbing; aggregate trail construction; stormwater drainage improvements including water bars, subdrain and rip-rap; three new pedestrian bridges including one (1) timber and two (2) pre-engineered steel bridges and concrete abutments; ADA sidewalk improvements; and new signage and wayfinding throughout the park.
Working days: 120
Specified start date: October 8, 2018
Substantial completion date: June 1, 2019
Final completion date: June 15, 2019
Liquidated damages: $500 per day
Rapids Reproductions
415 Highland Ave Suite 100
Iowa City, Iowa 52240
319-354-5950
$50 per plan set
Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.
Date: September 18, 2018
Time: 11:00 a.m.
Location: Hickory Hill Park Shelter, corner of Davenport Street and Bloomington Street
This meeting is non-mandatory.