Description:
The work will consist of improvements to Hebl Avenue between IWV Road and the Iowa City Landfill, including class 10 excavation, PCC paving, storm sewer, RCB box culvert, field fence, fiber optic conduit, seeding and associated traffic control and staging
Project Schedule Information:
Completion Date: October 27, 2017
Liquidated Damages: $500 per day
Date plans available:
Wednesday, May 17, 2017
Obtain from:
Engineering Division
City of Iowa City
410 E Washington Street
Iowa City, IA 52240
319-356-5140
Cost:
$25 per plan set
Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.
Pre-bid Conference:
None