Demolition of the existing restroom, storage and shelter facility and associated concrete slab and foundations. Following with the construction of two separate structures at Happy Hollow Park: A masonry building with a single-stall, ADA accessible restroom and mechanical space, with hardieboard siding and a stone veneer base. An open outdoor park shelter, of prefabricated wood and steel structure with douglas fir column and truss. Construction shall include, but not limited to: concrete foundations, masonry and stone wall, wood roof trusses, standing seam metal roof, mechanical, electrical and plumbing, site paving and finished site grading.
Substantial Completion Date: June 1, 2018
Final Completion Date: June 15, 2018
Liquidated Damages: $500 per day
Rapids Reproductions / Technigraphics
415 Highland Avenue, Suite 100
Iowa City, IA 52240
319-354-5950
$30 deposit per plan set. Deposit is refundable if returned within 14 days of Council award of project in re-usable condition.
Additional $15 shipping fee if mailed.
Date: January 16, 2018
Time: 11:00 a.m.
Location: Happy Hollow Park, Brown Street, Iowa City, Iowa