Description:
Construction of the Gilbert Street Pavement Repair – CRANDIC Railroad Crossing project includes removal and replace of the railroad crossing approach, pavement and sidewalk as well as new storm sewer and intakes.
Project Schedule Information:
Specified Start Date: August 1, 2022
Substantial Completion: August 19, 2022
Final Completion: September 2, 2022
Liquidated Damages: $500 per day
Date plans available:
Tuesday, June 7, 2022
Obtain from:
Technigraphics, a division of Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City, Iowa 52240
Phone: (319) 354-5950
Toll-Free: (800) 779-0093
https://rapidsrepro.com/iowa-city/
Cost:
None
Pre-bid Conference:
Date: June 23, 2022
Time: 2:00 p.m.
Location: Engineering Conference Room, City Hall, 410 E Washington Street, Iowa City, Iowa