Description: 

Construction of the Gilbert Street Pavement Repair – CRANDIC Railroad Crossing project includes removal and replace of the railroad crossing approach, pavement and sidewalk as well as new storm sewer and intakes.

Project Schedule Information: 

Specified Start Date: August 1, 2022
Substantial Completion: August 19, 2022
Final Completion: September 2, 2022
Liquidated Damages: $500 per day

Date plans available: 
Tuesday, June 7, 2022
Obtain from: 

Technigraphics, a division of Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City, Iowa 52240
Phone: (319) 354-5950
Toll-Free: (800) 779-0093
https://rapidsrepro.com/iowa-city/

Cost: 

None

Pre-bid Conference: 

Date:  June 23, 2022
Time:  2:00 p.m.
Location:  Engineering Conference Room, City Hall, 410 E Washington Street, Iowa City, Iowa

Project Status

Awarded

Awardee

Bockenstedt Excavating

Engineer's Estimate

$150,000

Bid Deadline

Tuesday, July 5, 2022 - 3:00pm

Council Award Date

Tuesday, July 12, 2022

Contact