Furnish all labor, equipment and materials required for traffic signal equipment removal and replacement and pedestrian sidewalk ramp improvements at the intersections of Gilbert St and College St and Gilbert St and Washington St. The project also includes the replacement of approximately 378 feet of 12” ductile iron water main pipe along Gilbert St from College St to Washington St, and street and pedestrian lighting removal and replacement along Gilbert St from College St to Washington St and along Washington St from Linn St to Van Buren St.
Overall
Specified Start Date: April 22, 2019
Final Completion Date: December 20, 2019
Liquidated Damages: $1,000 per day
Milestones
Stage 1 (water main)
Completion: July 26, 2019
Liquidated Damages: $500 per day
Stages 2 through 5 (All remaining work excluding signal and light pole erection)
Completion: October 31, 2019
Liquidated Damages: $500 per day
Technigraphics / Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City, IA 52240
319-354-5950
$30 per plan set. Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.