Description: 

980 feet of 8” PVC water main installed by directional drill method on First Avenue; 120 feet of 6” and 12” ductile iron water main installed by open trench and jack and bore method on Court Street; check valve installed in buried valve vault; and associated copper water services, traffic control, pavement removal, and restoration.

Project Schedule Information: 

Specified Start Date:  June 3, 2019
Substantial Completion:  August 16, 2019
Final Completion:  October 1, 2019
Liquidated Damages:  $500 per day

Date plans available: 
Wednesday, March 13, 2019
Obtain from: 

Technigraphics / Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City, IA   52240
319-354-5950
1-800-779-0093

Cost: 

$20 per plan set.  Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.

Pre-bid Conference: 

Date:  March 26, 2019
Time:  10:00 a.m.
Location:  Engineering Conference Room, 3rd Floor, City Hall, 410 E Washington Street, Iowa City, Iowa

Project Status

Awarded

Awardee

Dave Schmitt Construction

Engineer's Estimate

$375,000

Bid Deadline

Monday, April 8, 2019 - 3:00pm

Council Award Date

Tuesday, April 23, 2019

Contact