Description: 

Reconstruction of the 1st Avenue and Scott Boulevard intersection converting the existing four way stop into a single lane roundabout. Construction will include approximately 825 linear feet of storm sewer, 150 linear feet of water main, 5,500 square yards of concrete pavement, sidewalk improvements, street lighting, and restoration.

Project Schedule Information: 

Specified Start Date:  April 4, 2022
Substantial Completion Date:  July 8, 2022
Final Completion Date: September 30, 2022
Liquidated damages:  $1,000 per day

Date plans available: 
Wednesday, December 15, 2021
Obtain from: 

Rapids Reproduction, Inc.
415 Highland Ave.
Iowa City, IA 52240

Phone: (319) 354-5950
iowacity@rapidsrepro.com

Cost: 

None

Pre-bid Conference: 

None

Project Status

Awarded

Awardee

All American Concrete

Engineer's Estimate

$1,700,000

Bid Deadline

Tuesday, January 11, 2022 - 3:00pm

Council Award Date

Tuesday, January 18, 2022