Description:
Reconstruction of the 1st Avenue and Scott Boulevard intersection converting the existing four way stop into a single lane roundabout. Construction will include approximately 825 linear feet of storm sewer, 150 linear feet of water main, 5,500 square yards of concrete pavement, sidewalk improvements, street lighting, and restoration.
Project Schedule Information:
Specified Start Date: April 4, 2022
Substantial Completion Date: July 8, 2022
Final Completion Date: September 30, 2022
Liquidated damages: $1,000 per day
Date plans available:
Wednesday, December 15, 2021
Obtain from:
Rapids Reproduction, Inc.
415 Highland Ave.
Iowa City, IA 52240
Phone: (319) 354-5950
iowacity@rapidsrepro.com
Cost:
None
Pre-bid Conference:
None