Description:
Approximately 3,169 square yards of Portland Cement Concrete pavement, 223 feet of RCP storm sewer with related structures, 583 feet of water main with related fixtures, traffic control and other related work.
Project Schedule Information:
Phase 1 and 2:
Late start date: June 8, 2015
Substantial completion: July 15, 2015
Liquidated damages: $500 per day
Phase 3:
Completed: September 11, 2015
Liquidated damages: $500 per day
Date plans available:
Wednesday, April 22, 2015
Obtain from:
Engineering Division
City of Iowa City
410 E. Washington Street
Iowa City, Iowa 52240
319-356-5140
Cost:
$50 per plan set. Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.
Pre-bid Conference:
None