The Project will involve brick street reconstruction along Davenport Street between Clinton Street and Linn Street. The project will include the following: Excavation of 1,202 cubic yards of Class 10; installation of 633 feet of storm sewer and associated structures; installation of 460 feet of water main with associated valves, fittings and fire hydrants; paving 2,755 square yards of Brick pavers with a 1” HMA setting bed above a 7” PCC slab, and 736 square yards of sidewalk; as well as clearing and grubbing, site work, grading, and associated construction activities.
Start Date: June 19, 2017
Substantial Completion Date: August 11, 2017
Liquidated Damages: Incentive/Disincentive - $750 per calendar day ($10,000 max incentive)