Construction of Walden Green Community Gardens Improvements shall include, but not limited to proposed PCC pavement, site furnishings, and play structure installation, play surface installation, and associated work as shown on the plans. Alternates include: No. 1 - Climber: Landscape Structures Eclipse Climber. Contractor to purchase and install and No.2 - Shelter 12'x12' Coverworx Shelter. Contractor to purchase and install per manufacturer's recommendations.
Specified Start Date:
September 14, 2020
Substantial Completion Date: October 30, 2020
Final Completion Date: November 13, 2020
Liquidated Damages: $250 per day
Technigraphics
415 Highland Ave, Suite 100
Iowa City, Ia. 52240
319-354-5950
800-779-0093
Fax: 319-354-8973
None
None