Description:
This project involves the construction of approximately 534 linear feet of 8’ sidewalk near 2501 South Gilbert Street. This project includes, but is not limited to the following: removal of 97 SY of existing pavement; 363 CY of class 10 excavation; installation of erosion control measures, 714 SY of granular subbase, 499 CY of 8’ PCC sidewalk, 2 curb ramps, 41 SY of 7” PCC pavement, and 1450 SF of segmental block retaining wall with subdrain; placing and spreading of topsoil.
Project Schedule Information:
Early Start Date: July 24, 2017
Substantial Completion Date: September 29, 2017
Final Completion Date: May 15, 2018
Date plans available:
Thursday, June 29, 2017
Obtain from:
Technigraphics / Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City, IA 52240
319-354-5950
Cost:
None
Pre-bid Conference:
None