Description: 

Installing the connection of the electrical service equipment to the new underground service and removal of abandoned equipment at 27 residential properties.  Connection includes, but is not limited to, the conversion of the service entrance and meter base.  Connection will be coordinated with MidAmerican Energy and the City of Iowa City.

Project Schedule Information: 

Specified Start Date: April 4, 2022
Substantial Completion Date: May 30, 2022
Final Completion Date: June 14, 2022
Liquidated Damages: $250 per day

Date plans available: 
Tuesday, March 1, 2022
Obtain from: 

Rapids Reproduction, Inc.
415 Highland Ave
Iowa City, Iowa 52240

Phone: (319) 354-5950
iowacity@rapidsrepro.com

Pre-bid Conference: 

March 8, 2022 from 11:00 AM to 1:00 PM.  Meeting will be on-site.  Please email the Engineer for meeting location.  Masks are required to enter residences, no mask, no entry!

Project Status

Awarded

Awardee

Price Electric

Engineer's Estimate

$45,000

Bid Deadline

Tuesday, March 15, 2022 - 3:00pm

Council Award Date

Tuesday, March 15, 2022