Description: 

The project will involve watermain work including a check valve and associated vault structure along the west side of Prairie Du Chien Road, south of where Foster Road will be constructed.  The project includes, but is not limited to the following: a 6”x6” live tap, installation of 40 LF of 6” RJ DIP watermain, installation of 67 LF of 12” RJ DIP watermain, installation of 6’ I.D. check valve vault, installation of 12” check valve, installation of 12” valve, installation of one 12” fitting with thrust block, removal of 52 LF of existing watermain, removal and replacement of 43 LF of PCC curb and gutter, installation of 40 SF of 4” PCC sidewalk.

Project Schedule Information: 

Early Start Date:  March 15, 2019
Late Start Date:  April 1, 2019
Working Days:  20
Liquidated Damages:  $100 per day

Date plans available: 
Thursday, January 3, 2019
Obtain from: 

Engineering Division
City of Iowa City
410 E Washington Street
Iowa City, IA   52240
319-356-5140

Cost: 

None

Pre-bid Conference: 

None

Project Status

Awarded

Awardee

Carter & Associates

Engineer's Estimate

$55,000

Bid Deadline

Thursday, January 24, 2019 - 2:30pm

Council Award Date

Thursday, January 24, 2019

Contact

Document(s)