Description: 

The project involves the installation of one new traffic signal mast arm pole and footing at Iowa Highway 1 and US Highway 218 in Iowa City.  The project includes all materials, labor and equipment necessary for construction of project improvements.  Approximate quantities include:  1 combination traffic signal pole with 45’ mast arm and 15’ luminaire arm; 2 – 3 section traffic signal heads; 1 Iteris color video detection camera; 25’ of 4” PVC conduit; 31’ of pull rope, 1c #10 tracer cable, and #6 bare copper ground wire; 196’ of 1c #6 street light wire; 438’ of coax/power/focus video camera cable; 523’ of 4c #14 traffic signal cable; 1 – 3’ diameter by 11.5’ deep concrete signal pole footing;  removal of existing signal pole footing and wire, traffic control and miscellaneous related work.

Project Schedule Information: 

Project Completion:  10 working days after receiving traffic signal pole from the manufacturer

Phase 1 Start Date:  September 5, 2016
Completion Deadline:  October 31, 2016
Liquidated Damages:  $500 per day

Phase 2 Start:  Begins upon verification of new pole delivery on-site
Completion Days:  10 working days
Liquidated Damages:  $500 per day

Date plans available: 
Thursday, August 11, 2016
Obtain from: 

Rapids Reproductions / Technigraphics
415 Highland Avenue, Suite 100
Iowa City, IA   52240

Cost: 

$0

Pre-bid Conference: 

None

Project Status

Awarded

Awardee

Advanced Electrical Services

Engineer's Estimate

$25,000

Bid Deadline

Friday, August 26, 2016 - 2:00pm

Council Award Date

Friday, August 26, 2016