The project involves construction of 4-foot wide sidewalk along Highland Court adjacent to 424 and 1202 Highland Court, including the removal and replacement of roughly 20-feet of sidewalk adjacent to 1210 Highland Court. This project will also include driveway removal and replacement, installation of two trees, adjustment of a manhole, site restoration and other related work.
Project Schedule Information:
Specified Start Date: September 12, 2022
Final Completion Date: October 28, 2022
Liquidated Damages: $100 per day
Date plans available:
Friday, July 15, 2022
Obtain from:
Technigraphics/Rapids Reproductions
415 Highland Ave, Suite 100
Iowa City, IA. 52240
319-354-5950
800-779-0093
Cost:
Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.