Provide all labor, equipment and materials for the removal and replacement of pavement markings on First Avenue from US Highway 6 to Mall Drive; including and all other miscellaneous associated work.

Project Schedule Information: 

Specified Completion Date:  February 28, 2017
Liquidated Damages:  $200 per day

Date plans available: 
Monday, November 7, 2016
Obtain from: 

Engineering Division
City of Iowa City
410 E Washington Street
Iowa City, IA   52240
319-356-5140

Cost: 

$0

Pre-bid Conference: 

None

Project Status

Rejected

Awardee

No bids were received

Engineer's Estimate

$43,000

Bid Deadline

Friday, November 18, 2016 - 2:30pm