Description:
The project requires installation of ducts and handholes along First Avenue between Rochester Avenue & Scott Boulevard. The project also requires installation of optical fiber cable in the new and existing ducts and handholes between Rochester Avenue and Fire Station 4.
Project Schedule Information:
All project work shall be complete no later than October 15, 2015
Date plans available:
Monday, August 31, 2015
Obtain from:
Engineering Division
City of Iowa City
410 E Washington Street
Iowa City, IA 52240
319-356-5140
Cost:
$0
Pre-bid Conference:
None