Description:
This project includes, but is not limited to the following: 0.38 acres of grubbing, strip and salvage 303 CY of topsoil, excavate and dispose of 488 CY of Class 10 material, installation of 125 tons of rip rap, and 0.66 acres of temporary and permanent ground cover stabilization. The project site is located behind Dover Street adjacent to Mercer Park and the Iowa Interstate Railroad.
Project Schedule Information:
Pre-Construction Meeting: May 2, 2017
Early Start: May 9, 2017
Substantial Completion: July 5, 2017
Final Completion: September 15, 2017
Liquidated Damages: $250 per day beyond 65 working days
Date plans available:
Tuesday, April 4, 2017
Obtain from:
Technigraphics / Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City, IA 52240
319-354-5950
Cost:
None
Pre-bid Conference:
None