Description: 

The Project will involve reconstruction of curb ramps at 5 intersection locations in Iowa City.   The project includes all materials, labor and equipment necessary for construction of project improvements. 

Approximate quantities include:  154 SY of 4” PCC Sidewalk, 306 SY of 6” PCC Sidewalk, 95 SY 8” PCC Pavement Patch, 266 SF Cast Iron Detectable Warning Panels, 362 LF PCC Curb and Gutter, erosion control, hydroseeding, traffic control and miscellaneous related work.

Project Schedule Information: 

Early Start Date:  November 14, 2018
Late Completion Date:  April 15, 2019
Calendar Completion Deadlines:  40 Working Days
Liquidated Damages:  $200 per day

Date plans available: 
Wednesday, October 31, 2018
Obtain from: 

Rapids Reproductions / Technigraphics
415 Highland Avenue, Suite 100
Iowa City, IA   52240
319-354-5950

Cost: 

None

Pre-bid Conference: 

None

Project Status

Awarded

Awardee

Feldman Concrete

Engineer's Estimate

$80,000

Bid Deadline

Wednesday, November 7, 2018 - 3:00pm

Council Award Date

Wednesday, November 7, 2018