Description: 

This project includes, but is not limited to the following:  installation of pedestrian traffic control measure, removal of 103 SY of sidewalk pavement, installation of 685 SY of 6" PCC sidewalk, installation of 28.5 LF PCC retaining wall with limestone cap.  Site is located at the south entrance of City Hall.

Project Schedule Information: 

Pre-Construction Meeting:  May 23, 2017
Early Start Date:  May 30, 2017
Final Completion Date:  July 10, 2017

Date plans available: 
Monday, May 1, 2017
Obtain from: 

Engineering Division
City of Iowa City
410 E Washington Street
Iowa City, IA   52240
319-356-5140

Cost: 

Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.

Pre-bid Conference: 

None

Project Status

Awarded

Awardee

Feldman Concrete

Engineer's Estimate

$15,000

Bid Deadline

Tuesday, May 16, 2017 - 2:30pm

Council Award Date

Tuesday, May 16, 2017