Description: 

The project is funded with Community Development Block Grant Funds. The project involves reconstruction of curb ramps at 9 locations in Iowa City.  The project includes all materials, labor and equipment necessary for construction of project improvements.  Approximate quantities include: 2,996 SF of 4” PCC Sidewalk pavement, 1,176 SF of 6” PCC Sidewalk pavement, 315 SF Cast Iron Detectable Warning Panels, 385 LF PCC Curb and Gutter, erosion control, hydroseeding, traffic control and miscellaneous related work.

Project Schedule Information: 

Start Date:  June 17, 2016
Liquidated Damages:  $200 per day
Calendar Day Completion Deadline:  45 working days
Davis-Bacon Wage Rates shall apply

Date plans available: 
Tuesday, May 17, 2016
Obtain from: 

Rapids Reproductions / Technigraphics of Iowa City
415 Highland Avenue, Suite 100
Iowa City, IA   52240
319-354-5950

Cost: 

$25 per plan set
Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.

Pre-bid Conference: 

None

Project Status

Awarded

Awardee

Calacci Construction

Engineer's Estimate

$100,000

Bid Deadline

Friday, May 27, 2016 - 2:30pm

Council Award Date

Friday, May 27, 2016

Contact