Description:
Furnish all labor, equipment and materials required for replacement of two variable frequency drives for booster pumps; includes replacement of wiring, interfacing VFDs with SCADA system, hardware and programming modifications, and miscellaneous associated work.
Project Schedule Information:
Completion Date: October 27, 2017
Liquidated Damages: $500 per day
Date plans available:
Monday, April 24, 2017
Obtain from:
Veenstra & Kimm, Inc.
860 22nd Ave., Suite 4
Coralville, IA 52241
888-241-8001
Cost:
$0
Pre-bid Conference:
None