Description: 

This project includes, but is not limited to, construction of the following: a small play area with play equipment, 10’x10’ viewing tower with ADA compliant ramp, 1300 SF of 4” pavement, 3 display kiosks, 2 benches, and site landscaping. This project is located at the Iowa City Airport.

Project Schedule Information: 

Early Start Date: May 1, 2018
Final Completion Date: June 22, 2018

Date plans available: 
Monday, April 9, 2018
Obtain from: 

Technigraphics / Rapids Reproductions
415 Highland Avenue , Suite 100
Iowa City, IA   52240
319-354-5950

 

Cost: 

None

Pre-bid Conference: 

None

Project Status

Awarded

Awardee

Calacci Construction

Engineer's Estimate

$61,000

Bid Deadline

Tuesday, April 24, 2018 - 3:00pm

Council Award Date

Tuesday, April 24, 2018