Description: 

This project involves the removal and replacement of approximately 619 s.y. of 4" PCC and 126 s.y. of 6" PCC sidewalk located at multiple sites in Iowa City.

Project Schedule Information: 

Specified Start Date:  August 1, 2022
Final Completion Date:  October 31, 2021
Liquidated Damages: $50 per day

Date plans available: 
Friday, June 17, 2022
Obtain from: 

Engineering Division
City of Iowa City
410 E Washington Street
Iowa City, IA   52240
319-356-5140

Cost: 

None

Pre-bid Conference: 

None

Project Status

Awarded

Awardee

Feldman Concrete

Engineer's Estimate

$70,000

Bid Deadline

Friday, July 1, 2022 - 2:30pm

Council Award Date

Friday, July 1, 2022