Description: 

The project corridor is located at the Capitol Street Parking Garage and the Dubuque Street Parking Garage. The project generally includes concrete repair, weld tie repair, sealant replacement, and other miscellaneous items.

Project Schedule Information: 

Specified Start Date: July 6, 2021
Substantial Completion: September 17, 2021
Final Completion: October 1, 2021
Liquidated Damages: $100 per day

Date plans available: 
Friday, June 4, 2021
Obtain from: 

Technigraphics, a division of Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City, Iowa 52240
Phone: (319) 354-5950
Toll-Free: (800) 779-0093
https://rapidsrepro.com/iowa-city/

Cost: 

None

Pre-bid Conference: 

None

Project Status

Awarded

Awardee

Western Waterproofing

Engineer's Estimate

$108,000

Bid Deadline

Thursday, June 17, 2021 - 3:00pm

Council Award Date

Thursday, June 17, 2021